EYWA Tree of Life construction site, November 2026

Construction Update · November 2026

EYWA Tree of Life

Business Bay · Dubai

We are pleased to share the latest progress on EYWA Tree of Life. The structure is complete up to the roof. Internal works and building services are well advanced, and the facade and interior finishes are under way.

Tree of Life
52 residences
Way of Water
Updates coming soon

On site · November 2026

Site Film

A walk through the building this month: the facade across the elevations, kitchens, wardrobes and vanities going in, and passenger lift installation under way.

EYWA Tree of Life · site footage, November 2026 · 1:42
External Facade
Curved balcony edges
01 / 06 · Curved balcony edges
The tower from the street
02 / 06 · The tower from the street
View from Dubai Canal
03 / 06 · View from Dubai Canal
Side elevation
04 / 06 · Side elevation
Facade and cladding works
05 / 06 · Facade and cladding works
Looking up the facade
06 / 06 · Looking up the facade

Site photography, 17 November 2026.

EYWA Tree of Life

Overall Progress

Building B + G + 3P + 19 floors + roof
Residences 52
Workforce on site 557
RERA project no. 2621
65.66%
Construction complete
We are here
0%
25%
50%
75%

Independent inspection by Dubai Land Department, 22 October 2026.

EYWA Tree of Life

Progress Status

Completed
In progress
Upcoming

Completion of each work package per the main contractor's progress report, 31 October 2026.

Groundworks

Groundworks

4/4 completed
Mobilisation
Completed
100.00%
Enabling Works
Completed
100.00%
Piling & Foundation
Completed
100.00%
Substructure
Completed
100.00%
Structure

Structure

1/1 completed
Superstructure
Completed
100.00%
Envelope & Services

Envelope & Services

0/3 completed
Internal Works
In progress
88.41%
MEP
In progress
82.19%
External Building Envelope
In progress
56.01%
Finishes

Finishes

0/1 completed
Internal Finishes
In progress
34.58%

Programme

Updated Timeline

Completed
Mobilisation & Enabling
Completed
Piling & Foundation
Completed
Substructure
Completed
Superstructure
In progress
Internal Works & MEP
In progress
Building Envelope
In progress
Internal Finishes
In progress
External Works
To be announced
Handover